Blockader® Double Folding Gates Installation Instructions

  • For installation on concrete floors.
  • Bottom of gate hinges on bearing washer and pin set into floor hole. Do not remove bottom floor pin.
  • Top of gate hinges on "L" bracket bolted to wall or door frame
  • To install gates inside overhead doors, bollards or to clear obstructions, 6" or 9" extension brackets are required.
  • Optional "H" Bracket joins half of gate for added security
Parts provided with each gate:

Bearing washer makes bottom hinge 2" standard "L" bracket makes top hinge

Tools needed: Marking pencil, 3/4" masonry drill bit, 1/4" masonry or wood drill bit, drill, ratchet or wrench. Helpful tools include carpenters level and ladder.

Parts needed: 1/4” x 2” long lag bolts. Masonry door frame or wall installations may require lead anchors. 1/2” shaft diameter padlock.

Step 1: Before Installing decide on gate placement. “L” brackets that form top hinge allows gate placement in the recess of door frame. Installation can also be made outside or inside of wall next to door or opening frame. Either side of gate can be toward the outside of building. Put the “operating side” (the end with center drop pins) to the side used when padlocking the gate halves. A label on the operating side indicates RHT (right) or LFT (left) of a person facing the operating side.

Extension brackets (order separately) clear overhead door tracks, bollards or obstructions.
6” brackets provide 4-3/4” clearance,
9” brackets provide 7-1/4” clearance.

CAUTION
  • Keep fingers out of web pinch points.
  • Do not set gate on its wheel, gate will run away and fall,

Step 2: Have a helper extend the gate and stand it upright where it will be mounted.
CAUTION: Check to confirm gate will swing away from opening when not in use. This will provide a clear opening for normal traffic.

  • Drill 3/4” diameter x 3” deep hole, 1-1/4” from wall into the floor for gate pin to set into.
  • For 6” extension bracket drill 6” O.C. from wall.
  • For 9” extension bracket drill 9” O.C. from wall.

Place a bearing washer over floor hole and set
bottom gate pin into floor mount hole.

Step 3: Extend gate and hang “L” bracket on top of gate to verify where it will be mounted. To release tension you may lift the wheel 1/2”-3/4” off the floor. Mark and drill pilot holes into door frame or wall. It may be easier to drill pilot holes if you remove the gate from it’s floor mount. Place bearing washer and bottom gate pin back into floor mount. Slip “L” bracket over top of gate and bolt (bolts not included.)

  • Wood door frames or walls: 5/16” x 2” lag bolts.
  • Steel door frames or walls: Drill and tap for 5/16” x 2” lag bolts.
  • Brick or concrete frames or walls: 5/16” x 2” lag bolts set into 3/8” holes with lead anchors.
Step 4: Raise center drop pin and use attached notch to keep in place, this prevents damage to floor surface. Extend and retract gate to its stops to work out stiffness. Repeat steps 2-3 for other half of gate. CAUTION: Notice that center drop pin at this stage hits the other half of gate or rests on floor. Do not cut off drop pin. Step 5 addresses misalignment.
Step 5: With center drop pin raised, extend both halves of gates together to center of opening, mark floor for center drop pin hole and drill a 3/4” diameter x 3” deep hole. Lower center drop pin (Note: some larger gates have an additional pin in the center of each web, mark and drill these last.) Secure gate halves with 1/2” shaft diameter padlock. Open gates slowly at first to avoid warping.
Option: H bracket mounts overhead in center of gate. Extend both halves of gate together to
center of opening. Position “H” bracket, mark and drill pilot holes into mounting surface. Attach “H” bracket with bolts (not included.)
 
Copyright 2006 • The Tamis Corporation